Borik Residential Project. Construction Status Update [03.07.2025]
3. July 2025.
Borik Residential Project. Construction Status Update [08.09.2025]
8. September 2025.Construction Status Update – Borik Residential Complex
We are pleased to report continued strong progress on the construction of the Borik Residential Complex, as we move closer to completing a modern and high-quality residential development in the heart of Zadar’s Borik district.
Key Construction Highlights – July 2025:
Concrete Structure Completed
The reinforced concrete works across all buildings are now fully completed, marking a major milestone in the construction process.
Dividing Walls Installation
The installation of internal dividing walls is progressing steadily, defining the layouts of individual apartments.
Water, Sewage & Electrical Installations
Work continues on water, sewage, and electrical installations throughout the complex, ensuring essential infrastructure is in place for all units.
Aluminium Windows Installation – Building 2
The installation of aluminium windows has begun in Building 2, contributing to energy efficiency and the modern architectural design of the complex.
With each completed phase, the Borik Residential Complex moves closer to becoming a modern, sustainable, and premium living environment designed to meet the highest expectations of future residents.